THE CORPORATION OF THE CITY OF PORT COQUITLAM File No. 900-132 DATE: June 2, 1994 TO: Igor Zahynacz, P.Eng City Engineer FROM: Russ Mammel, EIT Supervisor of Design & Technical Services SUBJECT: Works Yard Off-Site Contract RECOMMENDATION: That Edvan Construction Ltd. be awarded the contract to construct the off-site works for the new City Works Yard and Fire Hall, for a tendered price of $270,750.00 including GST. Di a This project includes the reconstruction of Cameron Avenue along with a watermain and storm sewer, and the construction of two large diameter culvert crossings of the Broadway ditch. As shown on the attached suramary from CWMM Consulting Engincers, five contractors bid on this project. CWMM has recommended that the lowest tenderer, Edvan Construction, be awarded the contract, The tendered price of $270,750 for the off-site construction and supervision came in under the set budget of $320,000. As shown on the table below, $18,523 can be taken from DCC funds to contribute toward drainage and roadworks taking place on Broadway. Total DCC Contribution City Contribution Broadway Drainage Cost $38,979 $13,058 (33.5%) $25,921 (66.5%) Broadway Roadworks Cost | $13,044 $5,465_ (41.9%) SZL579__ (58.1%) | $52,023 $18,523 $33,500 ARMORES J.and Sale Reserve $252,227 DCC Funds £18,523 Total Tendered Cost $270,780 CC: Jeff Yip, P.Eng Deputy City Engineer