September 10, 1990/249 From the City Engineer, August 23rd, 1990 regarding Beaconcare Development - Servicing Cost Sharing. Moved by Alderman Lakine: Seconded by Alderman Gates: 1. That Council approve the request from Civic Consultants Ltd. to award the Contract for the installation of the services for Beaconcare Development to TRS Construction Services Ltd. That Council approve the allocation of the following amounts as the City's share of the installation of trunk services to the Beaconcare Development: ae $180,926.00 from the Tax Sale Reserve Fund for roadworks. b. $10,320.00 from the Area No.3 Sewer DCC Reserve Fund and $1,680.00 from the Sewer Capital Reserve Fund for the sanitary sewer. $4,200.00 from the Area No.3 Water DCC Reserve Fund and $2,800.00 from the Water Capital Reserve Fund. Carried. From the City Engineer, August 23rd, 1990 regarding Placement of New Stop Signs - Citadel. Heighrs. Moved by Alderman Laking: Seconded by Aiderman Gates: That Council approve placement of new stop signs at the following intersections: ae at Fortress Drive for traffic entering Citadel Drive; at Fortress Court for traffic entering Citadel Drive; at Muskett Terrace for traffic entering Fortress Drive; at Fortress Drive for traffic entering Fortress Court. Carried. Fasten anean samen canermanimened From the City Engineer, August 23rd, 1990 regarding Placement of Large Street Signs at Major Intersections. Moved by Alderman Laking: Seconded by Alderman Gates: l. It is recommended that Council approve the installation of two large street name signs on the existing metal traffic poles at the intersection of Mary Hill Road and Pitt River Road, showing the location of the Mary Hill Road intersection for traffic travelling along Pitt River Road. It is recommended that Council allocate $300.00 from the 1990 Public Works Capital Fund for these signs.