wi ph eae Are ach Wate ne ee ttre Ae aM ; ead ih t ig Re a i dt Nan THE CORPORATION OF THE CITY OF PORT COQUITLAM MEMORANDUM Igor Zahynacz, P.Eng. City Engineer Andrew de Boer Project Engineer July 23, 1992 As requested I have contacted the consultant, KPA Engineering to provide clarifications on the subject project: Traffic Control - temporary signal lights will be installed on Kingsway to permit one-lane traffic on a 24 hour a day basis. Flag persons will be used where required Schedule - the work on the bridge deck on Kingsway will take approximately two weeks per lane for a total of 4 weeks. The cosmetic work on the deck soffit (underside) will require one-lane closure of the underpass for approx. 2 hours. Working Hours - the work will be done during the daytime but there may be some late evening or early moming work, depending on the weather. Web Andrew de Boer Project Engineer