THE CORPORATION OF THE wow.) CITY OF PORT COQUITLAM FEB 14 1994 REPORT TO COUNCIL MEMORANDUM TO: J. Maitiand DATE: Febmary 10, 1994 Acting City Administrator FROM: LR. Zahynacz, P. Eng., FILE: PWC City Engineer SUBJECT: COST SHARING OF ROAD PAVING - 2349 CENTRAL AVE. AND 2223 WELCHER AVE. (Public Works Committee Meeting - February 8th, 1994) RECOMMENDATION: That Council approve the expenditure of $3.584.50 (including GST) towards the reinstatement of the southem portion of the road pavement in front of 2349 Central Avenue. That Council approve the expenditure of $3,163.99 (including GST) towards the reinstatement of the southem portion of the road pavement in front of 2223 Welcher Avenue. That Council allocate $6,748.49 from the Special Public Works Capital Reserve Fund for this purpose. Two townhouse developments. one at 2349 Central and one at 2223 Welcher are required to repave the street in front of the development a distance of half the roaaway plus a meter. Porter Construction Ltd. has submitted a quote of $3,584.50 (including GST) to pave the remaining two meter wide asphalt strip in front of 2349 Central Ave. and Jack Cewe Ltd. has submitted a quote of $3.163.99 (including GST) to pave the remaining two meter wide asphalt strip in ‘front of 2223 Welcher Ave. Attached are quotes from Porter Construction Ltd. dated January 27, 1994 and Jack Cewe Ltd. dated February 1, 1994. This work would include saw cutting, removing of existing asphalt. reconstructing the 3/4 inch gravel base and paving with hot mix asphalt. ; IRZ:ca Attachments Treasurer’s Comments: There are sufficient funds in the Special Public Works Capital Reserve Fund for this purpose. J. Maitland City Treasurer