12 hereof as the estimated current cost of each such Phase res- pectively, and each said deposit shall be a condition precedent to the approval of the subdivision of that portion of the land included in that particular Phase of the subdivision and develop~ ment thereof, The Developer agrees that if the works Specified nerein are not completed pursuant to Section 12 hereof, the Municipality may complete the works at the cost of the Devel- oper and deduct from the deposit held by the Municipality the cost of such completion, and the balance of the deposit shall te returned to the Developer, less any administration fees required. If there is insufficient money on deposit with the Municipality, then the Developer will pay such deficiency to the Municipality immediately upon receipt of the Municipality's Bill for completion. Ir is understood that the Municipality may do such work either by itself or by contractors employed by the Municipality. If the works are completed as herein provided, then each said @eposit, less administration fees, shall be returned to the Developer. Uporading of Public Works: 14. To facilitace the use and development of the land, the Deveioper covenants and agrees to contribute to the Munic- ipality prior to registration of this Land Use Contract in the Land Registry Office the following sum of money, being the amount required to defray the excessive costs incurred by the Municipality for the following purpose: {a) $50,000.00 for the provision, installation and construction of storm sewers, curbs, boulevards and pavement on Pinley Street; and $100,000.00 for the provision, installation and construction of a watermain on Prairie Avenue from Newbury Street to Freemont Street, all made necessary by the increased population, traffic density and service reguirements created by subdivision and development works, and it is understood and agreed that the Municipality will carry out and complete the said works at such time or tines as shall be within the sole discretion of the Municipality, Maintenance of Works by Developer: 15. The Developer covenants and agrees tc: (a) Maintain all of the said works to be built pursuant to this Contract in complete repair for a period of one (1) year from the completion thereof as certified by the Municipal Engineer. (b) Remedy any defects appearing within the period of one (1} year from the date of such completion of the said works and pay for any damage to other work or Property resulting there- from save and except for defects caused by reasonable wear and tear, neglicence of the Municipality, its servants or agents, or act of God, and (c} Deposit with the Municipality, prior to the release of each security pursuant to Section 13 hereof, for a period of one (1) year from the completion of that portion of the said works included in that particular Phase and Development Agreement and as certified by the Municipal Engineer, a sun equal to ten percent (10%) of the total estimated cost thereof, and should the Developer fail to maintain the said works, remedy any de- fect or pay for any damage resulting thereZron, the Municipality may deduct the cost of completing the said works; remedying the defect or paying the damage from the said deposit. Ownership: 16. All works and services (save and except gas, tele- Phone and electricity), buildings, structures, Pipes, fixtures and things, and development constructed, placed or carried out upon property that now is vested in the Municipality or located upon highways presently dedicated or by this Contract recuired