‘fr. Igor Zahynacz, P.Eng. ; Page Three City of Port Coquitlam September 4, 1990 Construction Cost Estimate Gravity Line construction of 525 m + of 300 mm ¢ gravity sewer $160,000 asphalt repairs (3200 m?) 80,000 imported backfill (5200 m°) 52,000 extra for tie-ing to existing 3,000 Sub-total $285,000 Plus 15% Contingency 43,000 Total (a) $328,006 b) Uperading of Freemont Pump Station Standby Generator $ 75,000 Plus 16% Contingency 11,000 Total (b) $ 86,000 The total construction cost is estimated at $414,000 to divert sewage from Handley P ump Station to Freemont Pump Station. Thia amount does not include provision for sheet piling, well pointing and the possibility of supporting sections of the sewer line on piles. The estimate also assumes that the existing pumps at Freemont will be kept in use for the next 5 to 19 years. A $40,000 allowance should be provided for upgrading tho pumps and electrical system for future PWWF as required. This compares with the tendered amount of $383,516 for the construction of a new Handley Crescent Pump Station. Please let us know if we can provide further details. Yours truly, DAYTON & KNIGHT LTD. Jack Lee, P.Eng. ITEM {| PAGE | \\4|