3.96 We considered two North-East Sector Plans to provide the minimum service to the Camex proposal, while improving water supply throughout the entire area of existing and potential development on one-acre parcels. Alternative One is a sector water System built around a 75 1/s Capacity pumping station (two duty pumps) and a 1666 cubic metre reservoir (TWL 140 m) a component/budget grid has been deve loped. NEW . 75 1/s pumping station at Mason oo and Oxford $150,000 to $200,000 ENLARGE to 40 1/s existing pumping station at David Avenue (Coast Meridian No.1) ; $125,000 to $150,000 1666 cubic metre reservoir at Queenston Avenue. (TWL 140 m) $230,000 to $250,000 200 mn reservoir supply main on Coast Meridian from Queenston to David $75,000 $90,000 200 mm distribution main on Millard from Coast. Meridian to Camex . _ $25,000 $35,000 - 200 mm interconnection of 200 mm on Mason Avenue from Wellington “to Coast Meridian ; $25,000 $35,000 RANGE OF COSTS : | $630,000 $760,000 We think that the Camex proposal could Proceed on the basis of the initial construction of Item A, the new sector pumping Station at Mason and Oxford. Other elements of the system would-be added progressively as sewerage is extended. - wwe Te eget ee kms sakes ys% y a cant etmene ‘ : oe CEH OSE N Cee STFA Pott SOC ea a mi Tome nen eae ih