we Should Council decide to reject all tenders and have the work done by City forces we expect that our final cost for the job would be $462,960.00 based on the use of the material available at 1734 Broadway and on the estimated quantities. We have checked with CEWE to see whether they would be Prepared to: use the on site material-and So reduce their unit price. They are not prepared to do so because of the extra cost of mobilizing on two Sites. Normally, on that the difference is not ng the chance that. our estimated One further point for clarification is that the final price for the project regardless of who does the work will not be the tendered amount but will be the actual qQuantities used on site multiplied by the unit prices. -We think we have estimated the quantities on the high side but we could-be wrong. In any case the total should be well. below the $700,000.00 allowed in the budget. FE. Petérs, P.Engz> City Engineer