ee d) tem C-2 Maple Leaf Construction’s price for installing catch basin leads is low at $65/m. The other two tenderers priced this item over $130.00/m. e) kem C-3(c) Jack Cewe's price for installing manholes is unreasonably high at $3,038.80. . ttem C-7(b) Maple Leaf Construction’s price of $45/m for installing lawn basin pipes is half of the average tender price of $90 submitted by the other two tenderers. Item 0-3(a) — Porter Construction’s price for installing bends is exceptionally high a $2,100 and out of balance. tem 0-6 “Maple Leaf Construction’s price of $4,300 for installing steel dogleg fittings is high compared to the other two tenderers whose price bid not exceed $3,200. Item D-9 Porter Construction’s price of $800 for installing service connections is very low when cornpared with the other tenderers whose prices were in excess of $2,300. Item D-11 Maple Leaf Construction price for removing the abandoned PRV station is unreasonably low. The average price submitted by the other two tenderers is $2,190 while Maple Leaf Construction’ S$ price is $560. tem E-5 Jack Cewe's price for installing junction boxes of $79.20 is roughly half that of the other tenderers. Item F-2 dack Cewe's price for installing system loop conduits is extremely high at . $9.76 roughly 4 times the price @ of the average of the other two tenderers.