THE CORPORATION OF THE CITY OF PORT COQUITLAM C 0 UJ Ni JUN 39 B. Kirk, DATE: May 30, 1983. City Administrator. c.c.: TT, Chong, Library Construction Assistant City Engineer. Committee. SUBJECT: ‘Upgrading Mary Hill Road. RECOMMENDATION : That we recommend to Council to proceed with upgrading Mary Hill Road between Atkins and Wilson as outlined below with the $57,000 cost to come out of the $1,750,000 appropriated from the Tax Sale Reserve. BACKGROUND & COMMENTS: ; See ; . Specific items.included in the $57,000 estimate are: 1. Sidewalk on east side of Mary Hill Road. 2. Curb and gutter on east side of Mary Hill Road. 3. Relocation of up to five utility poles. 4. Installation of three new catch basins. 5. Landscape the boulevard on the east side of . Mary: Hill Road. ‘ 6. 4 two inch asphalt overlay from curb to curb. 7. Redo the sidewalk, curb and gutter on the south _ side of Wilson from Mary Hill Road to the Wilson Centre parking lot entrance. We would have required a developer to provide most of the above if this were a private building. Alsc, these improvements will enhance the appearance of the new Library. If spéedy approval is granted, we should be able to com plete the works prior to the library opening. (OR a aE EES wieg ap yeh MONA Hamat a Toe RAH A te