THE CORPORATION OF THE CITY OF PORT COQUITLAM TO FROM: SUBJECT: MEMORANDUM Igor Zahynacz DATE: Oct 16. 14, 1992 City Engineer Ike De Boer PROJECT: 559 Project/Traffic Technician Kitchner/Davies Traffic Improvement Implementation 2) 3) 4) Listed below is a summary of the Urban Systems recommendations and the estimated costs for the traffic improvements in the Kitchener/Davies area, A) Patricia/Hastings/Woodland 1) Install temporary traffic circle at Patricia and Murchie, remove barricades on Murchie and a section 6f median barrier at Woodland and Kitchener, install traffic sign on Kitchener approx. costs for this work = $7,106 Install speed humps on Jervig, Raliegh and Lancaster complete with associated gignage at an approx cost of $7,500 Install a temporary traffic circle at Hastings and Kitchener only after a review is done of the circle at Murchie and Patricia, approx cost $5,000 Reconstruct Hastings and Patricia to full standards at an approx cost of $337,000 B) Hastings/Davies (south of Lougheed) 1) The installation of a temporary traffic circle at the 2) intersection of Raliegh and Davies, again a reveiw of the Patricia/Murchie circle will be done prior to a circle placed here, approx cost $5,000 Construct a right turn lane on the east side of Westwood at Lougheed at an approx. cost of $51,500 Reconstruction of Davies and Hastings to full standards at an approx. cost of $430,000