-7-

any material or debris should be deposited upon any road during the

construction of the work or should the construction by the Developer

constitute a nuisance to neighbouring properties of the work the Developer
covenants and agrees that the Municipality may forthwith remove such
material or debris or put right such nuisance at the expense of the
Developer, the cost thereof to be determined by the Engineer. In the

event that construction of the work ceases for any period of time in

excess of thirty days the Developer covenants and agrees that the Municipality
may forthwith enter upon the property and construct thereon a solid

board fence not greater than eight feet in height nor less than six feet

in height surrounding the entire perimeter of the project and that in 50
doing the Municipality accepts no responsibility for the suitability or.
adequacy of the said fence erected for the benefit of the said Developer
and for which the Developer covenauts and agrees to accept full responsibility
and to save harmless the Municipality from each and every action and

claim which may be brought or arise as a result thereof. In the event

that any invoice of the Municipality for the removal of such material ‘or
debris or construction of the fence shall remain unpaid after thirty

days of receipt of the same by the Developer the Municipality is authorized
to deduct the amount of such invoice from the deposit referred to in
Section 13 hereof.

16. Subject to this agreement, the within works and the development

herein shall comply with all the By~laws of The Corporation of the City

of Port Coquitlam.

17. Notwithstanding any provisions of this contract, hereinbefore contained
and notwithstanding the provisions of the "City of Port Coquitlam Building
and Plumbing Code Administration By-law, 1974, No. 1298" and of Section

714(k) of the "Municipal Act", R.S.B.C., 1960, Chapter 255 and amendments

thereto, the Developer covenants and agrees that the Municipality may
withhold the granting of an occupancy permit for the occupancy and/or
use of any building or part thereof, constructed upon the said lands

until all of the works herein have been completed to the satisfaction of

the Engineer.
18, (a) The Developer agrees to pay all arrears of taxes outstanding
against the property herein described before the formal approval

of the said scheme of use and development upon the land is