after granular base materials, dampproofing membrane
and if applicable, reinforcing steel has been placed
for the inatallation of a concrete floor slab but
prior to placing of concrete;

10.2.4. before a building drain, sanitary or storm sewer is
covered, and if any part of a plumbing system is
covered before it is inspected and approved it shall
be uncovered if a Building Inspector so directs, and
when considered necessary, underground building
drains, branches, storm drains, and sewers shall be
re~tested after the completion of all backfilling
and grading by heavy equipment;

10.2.5. when framing and sheathing of the building are
complete, including fire-stopping, bracing, chimney
duct work, plumbing, gas venting, wiring, but ~“:fore
any insulation, or other faterior or exterior nish
Ls applied which would conceal such work;

after the placing of insulation and vapour barrier
but before any interior finish is applied; and

after the building or portion thereof is complete
and ready for occupancy, but before any occupancy of
the building.

Prior to the occupancy of any building or part thereof after
construction or alteration, or any change in clases of
occupancy, the owner or occupier shall obtain an occupancy
inspection from a Building Inspector, which shall not be
complete until the building or part thereof complies with the
requirements of this Bylaw and all other requirements relating
to the construction and occupancy of the building.

In all cases where it is proposed to conduct the waste from
plumbing fixtures, trade waste or surface or roof water to a
public sewer the Owner. shall ensure that such public sewer is
at a sufficient depth and of a capacity to receive such
discharge; and shall arrange the plumbing to suit the location
of the connection provided for the lot.