The volume of material required to fill the area for the Phase I development is approximate.ly 250,000 m5. This will be approximately 25.000 truck and trailer loads of material at the rate of 75-100 loads per day. The Phase I fili operation will take approximately two (2) years to complete. The Orciving Range site will be completed first. with the Mobile Home Park to follow. Concerns of the Local Residents All residents of the immediate area will be contacted and informed of the work to be undertaken. All work will be conducted during working hours, a3 per City of Port Coquitlam bylaws. A dust control program will be maintained, consisting of sweeping and flushing on an 43s required basis. Access to the site will be controlled with a set of locking gates. Quality Control Al} construction on the Kwayhquitiam Lands will be constructed in he City of Port Coquitlam Engineering specifications and the 8.C. Building Code, any geotechnical advice will be provided by a Geotechnical Consulting Engineer. An Environmental Consultant will be retained to advise on any potential environmental impact the deve lopment may have. 41DWN79